15th May Bridge - Cairo  - Egypt
                    
                    
                        Bridges & Flyovers
                          ::  Completed Projects
                          ::  2000  ::  
                    
                    
                    
                    
                        
                            Owner: Cairo Governorate – Department of Roads and Bridges. 
   Contractor: The Arab Contractors (Osman Ahmed Osman & Co.) – Bridges Department 
   Consultant: The Arab Consulting Engineer  Dr. A . Moharram – Dr. M. Bakhoum Misr Dywidag
  Date of handling over: 20 April 1986 
   Description: The elevated road connects Abu El-Ela and Zamalek bridges   and flies over 26 July Street at Zamalek. 
   Length: 1100 meters 
   Width: 16.60 metes 
    Number of columns: 39 columns spacing 25 meters 
   Foundation: 200 bored piles 
   Superstructure: Prestressed concrete. 
   Type of prestressing: 
 - Dywidag single bar tendons ? 36mm. steel 835/1030 in                                                    upper and lower slab.
 - Dywidag multiple strand tendons 12 ? 0.6 inches steel                                                     1570/1770 in webs. 
System of Construction:
  Deck Pushing System for the first time in Egypt                                                       Without inconvenience of traffic in 26 July street in Zamalek