Saida Wastewater Plant - Phase 1 - Lebanon

Water & Wastewater   ::  Completed Projects   ::  2005  ::  

Phase 1- Contract 2208
(Construction of Wastewater Collection System and Treatment Plant)

Original Contract Value : 9,492,595.44 USD
Modified Contract Value : 10,744,913.85 USD
Starting Date : 21 July 2001
Contract Period 728 days (24 months)
Date of Completion : 18 July 2003
Extension of Time22 Months (due to VO # 1 & 2)
Date of Completion : 19 May 2005.
Date of Final Hand Over : 19 May 2006

Wastewater Treatment Plant ( WWTP )
Saida Coastal area wastewater treatment plant is designed to remove solid material by screening and grit removal and sand from sewage water ( Primary Treatment ). The max flow : 1511 L/S at year 2030 Service Population : 500 000 at year 2030

WWTP consists of 6 Building :-
Inlet Lifting pump station T1
Outlet Pump station T2
Screening house area
Electrical Building
Administration building.

Description of Processing Wastewater comes from three point :-
1- Three Main Pump station M1, M2 ,M3
2- Five Local Pump station south area L5,L3,L2,L1 and north area L10
3- Network from Saida area about 160 Km Gravity pipe .

Sewage enters the plant at pump station T1 from said area sewer line to fine screen 6 mm opening .

Electrical Building
One Generator stand by 1280 KVA