Accomplishment of the 7th Sector Works in Cairo-Alexandria Desert Road by the End of June

Eng. Mohsen Salah – AC Chairman toured the development of the 7th Sector in Cairo-Alexandria Desert Road starting from El Amiriya kilo 190 till the entry of Alexandria 30km long. His tour to assure that the work progress is in accordance with the condensed schedule stated by the Transport Ministry to accomplish the project by the end of June.
It is noteworthy that the national authority for roads, bridges and land transport is supervising the project. The project scope of work is the  the development of 4 lane on both sides. In addition to the construction of industrial structures includes: 5 bridge - 5 flyovers - 5 pedestrian bridges. Those structures will be executed by the roads, bridges and manufacturing sector; and Alexandria branch in the Arab Contractors Company with a total cost EGP 810 million.