Mubarak Peace Bridge - East Bank.
_________________________________
Construction of over
Suez Canal Bridge at Quantara, Egypt first major fixed connection between Sinai
and the rest of Egypt. The works has been commissioned to 3 contractors, The Arab
Contractors is in the East Side(i.e in Sinai).
The scope of work
includes the construction of 1080m Prestressed box girder concrete bridge plus 3830m
embankment and road connecting the bridge with Al-Ferdan-Rafah Highway.
Tendons :
(550ton)12 strands 0 0.62inch steel 1770. The Engineer: A consortium of two Japanese
Consultants (i.e PCI and CHODAI) in association with A.C.E. |
 |
El-Warrak Bridge
_________________________________
The bridge
connects the east bank of the Nile (Cairo-Kanater road) with the west bank (Embaba-Kanater
road) running over the Nile and the north side of the Warrak island. The length
of the bridge is 2.250 km. The bridge has 4 ramps in the western side
Tendons :
(3000 ton) 12 strands 0 0.62 inch steel 1700
|
 |
El- Moneeb Bridge
_________________________________
It is
considered the largest bridge. crossing the Nile in length & wideness of navigation
spans. It connects Cairo easterly and Giza westerly. It is one of the most important
axis of the ring road around Greater Cairo. This bridge connects Alexandria desert
road, Fayoum, 6th of October City, east and west bank of the Nile, south Giza and
upper Egypt. The bridge has 6 inlet and 6 outlet ramps. The length of the bridge
is 2km its width is 42m.
Tendons:
(2397ton)12 strands 0 0.62inch steel 1770. (988 ton) 19 strands 0 0.52inch steel
1860. (609ton)Bars 0 36mm steel 1030.
|
|
|
Banha Bridge
_________________________________
The project consists of a tunnel, bridge works and a road 5.5km. Long.
First : 2Elevated pre-stressed concrete bridges.
- One crossing Damietta branch and
Banha-Zefta railway , 1300m long with a navigation vent of 120m wide .
- The second crossing Elrayah El
Tawfiky, length of the concrete part is 135m and the navigation vent is 57m wide
.
- The total width is 26m (3 lanes
in each direction).
Second: The roads :
joining the Nile bridge and El-Rayah bridge with Cairo-Alexandria agricultural road
with total length of 4325m.
Third : Cars tunnel:
On Kafr saad road and another for the pedestrians.
40m long, 10m wide in both directions and 4.25m high.
Tendons : (1116 ton) 19,12 strands 0 0.62 inch steel 1770. The
Engineer: Dar El-Handassa
|
 |
Stanly Bay Bridge - Alexandria
_________________________________
In Egypt
it is the first bridge to be constructed into the sea, with a total length of 400
m, consisting of 6 spans .It constitutes a major part of the reconstruction and
decoration of Alexandria corniche. A master piece of architecture precision, the
bridge preserves the architectural style of Egypt. The scope of work includes: Offshore
deep foundation (Bored Piles) to support Stanly bridge, 102 piles 100cm dia. 28m
depth & 98 piles 150cm dia. 35m depth.
Tendons :
250ton 12strands (0.62inch) steel 1770
|
 |
The Indoor Sports Hall Complex
- Cairo
_________________________________
The project consists
of 4 Halls as follows : -The main hall is covered with a dome of 125 m. diameter.
The dome is formed by 3 portions,
each portion is loaded on a steel truss ring beam, The height of 1st portion is
9 m., 2nd portion height is 5 m and the 3rd portion height is 3.8m as a sky light
with a special mechanism system.
The pre-stressing cables are
used in forming the dome shape in addition to beaming function.
The dome is cladded with aluminum
rids, sheets and rock-wool.
-The medium hall is covered
with a dome of 54m. diameter.
-The twin small
halls are covered with a dome of 27m. diameter each.
Tendons :
(270 ton) strands 0 0.62 inch steel 1770
|