Salvage of Hibis Temple
El-Wady EI-Gadeed
_________________________________
The scope of work includes construction of horizontal drainage gravel filter
wall around the temple of 13m depth and 80cm thick.
|
 |
EI- Tahreer multi-storey Carpark (Egyptian museum):
_________________________________
The project lies in front of the Egyptian Museum on area of 21000 square meters
and consists of 4 underground stories. The scope of work includes: Side support
and pemanent structure water tight walls to allow excavation of 18m below ground
surface for the construction of 4 underground stories carpark. Diaphragm wall 80
and 100 cm thick of total surface area of 6000m 2, Barrettes and slurry walls.
|
 |
EI- Orouba Tunnel
_________________________________
The project comprises the uni-direction main tummel., 2 inlet ramps & 2
outlet ramps. It provides free connection.
|
 |
EI- Thawra Underpass
_________________________________
The project Greats a free inter section by passing the Thawra street under
EI-Orouba road.
|
 |
Esna additional navigation lock
_________________________________
Diaphragm wall T section to support 17 meter excavation side with total
depth of 42m canteliver tgpe and diaphragm wall rectangular sec. with 2¬3 rows of
anchors to support 17m ecavation on the other side.
|